UCSD CAMPUS NOTICE University of California, San Diego |
|
FACILITIES DESIGN & CONSTRUCTION December 17, 2003
SUBJECT: CONSTRUCTION ALERT - Voigt Drive Beginning on December 29, 2003 the Computer Science and Engineering Building will be installing the steel erection crane on the site. Several large flat bed trailers will be accessing the site from Voigt Drive. Structural Steel erection will then begin and extend from Dec. 29, 2003 to April 30, 2004. We anticipate anywhere from two to four flatbed truck deliveries per day. Flagmen will be responsible for traffic control along Voigt Drive for the duration of the steel installation.
Please view the area map at If you have any questions, please contact, Michael Downs, Project Manager at 858-534-4094. We greatly appreciate your patience during these construction activities.
|