UCSD
CAMPUS NOTICE
University of California, San Diego
 

OFFICE OF THE ASSISTANT VICE CHANCELLOR -
FACILITIES DESIGN & CONSTRUCTION

January 14, 2005


ALL ACADEMICS AND STAFF AT UCSD

SUBJECT:    CONSTRUCTION ALERT - Osler Lane

Project Description/Location

The Pharmaceutical Sciences Building is currently under construction at the School of Medicine. As part of this construction project, the contractor will be installing roof top HVAC equipment. This work will take place from Thursday, January 20th through Friday, January 21st, beginning at 6:30 a.m. and ending at 3:30 p.m. each day.

Immediate Street Impacts

During this time, 5-6 tractor trailers will arrive with crane and HVAC equipment to be off-loaded. While there will be no road closures, Osler Lane will be reduced to one lane at times during these days. A flagman will be present to direct traffic at all times.

If you have any questions, please contact the Project Manager, Mark Rowland, at 858-822-0725 or Project Specialist, Nancy Sillman at 858-534-2981. We greatly appreciate your patience during these construction activities.

Please view the area map at:
http://www.fdc.ucsd.edu/alerts/files/Pharmaceutical.pdf

M. Boone Hellmann, FAIA
Assistant Vice Chancellor
Campus Architect
Facilities Design & Construction