SUBJECT:    CONSTRUCTION ALERT - Osler Lane

Project Description/Location

The Pharmaceutical Sciences Building is currently under construction at the School of Medicine. As part of this construction project, the contractor will be removing the tower crane. This work will take place on Friday, November 12th and Saturday, November 13th, beginning at 6:30 a.m. and ending at 3:30 p.m. each day.

Immediate Street Impacts

During the dates noted above, Osler Lane will be reduced to one lane at times. A flagman will be present to direct traffic at all times.

If you have any questions, please contact the Project Manager, Mark Rowland, at 858-822-0725 or Project Specialist, Nancy Sillman at 858-534-2981. We greatly appreciate your patience during these construction activities.

Please view the area map at:
http://www.fdc.ucsd.edu/alerts/files/Pharmaceutical.pdf

M. Boone Hellmann, FAIA
Assistant Vice Chancellor
Campus Architect