UCSD CAMPUS NOTICE University of California, San Diego |
||||
FACILITIES DESIGN & CONSTRUCTION April 6, 2004
ALL STUDENTS AT UCSD
Project Description/Location EBU-3B Computer Science and Engineering is currently under construction. In order to facilitate the installation of pre-cast panels, a portion of Warren Mall between EBU-2 and the project site will be closed to pedestrian traffic from 7:30 a.m. on May 3, 2004 to 4:00 p.m., May 6, 2004. Pedestrian traffic from Warren Housing to the main campus will be diverted through the courtyard of EBU-2. In addition, the contractor will close the east-bound lane on Voigt, adjacent to the construction site, from 7:30 a.m. on May 5, 2004 through 4:00 p.m., May 11, 2004. This closure will be in effect during regular work hours, then re-opened in the evening. All flagmen and signage will be in place for this operation.
Please view the area map at If you have any questions, please contact the Project Manager, Michael Downs, at 858-534-4094. We greatly appreciate your patience during these construction activities.
|