Project Description/Location The Music Building is under construction and the Contractor will need to make electrical and fire hydrant connections between the building site and the existing utilities located under Russell Lane. Immediate Street Impacts The utility installation will require traffic control related to Russell Lane. Motorists will experience temporary vehicular delays while this construction is taking place. The work is scheduled to start July 17, 2007 and continue to approximately August 7, 2007. Flagmen will assist vehicular coordination during work hours and steel trench plates will be installed after hours to enable traffic to flow freely. Please view the area map at: If you have any questions, please contact the Project Manager, Michael Downs (858-534-4094) or Project Specialist, Laurel Foster (858-822-3704). We greatly appreciate your patience during these construction activities.
|