SUBJECT:    CONSTRUCTION ALERT EXTENDED SCHEDULE – Bonner Hall Utilities Roadwork at the Intersection of Gilman Drive and Eucalyptus Grove Lane and Eucalyptus Grove Lane to Bonner Hall

Project Description/Location:

The Bonner Hall Utilities Roadwork which began Monday, March 11 at the intersection of Gilman Drive and Eucalyptus Grove Lane and west to Bonner Hall will be extended through Friday, April 12, 2019, to include the installation of new underground piping. The roadwork is part of the Condensate Recovery Project which will capture air conditioning condensate from York, Mayer, Urey, and Bonner Halls air handling units and will pump the recovered water into the campus reclaim system for non-potable usage including landscape irrigation. The collected water will be routed from Bonner Hall to the campus reclaim water distribution system on the East side of Gilman Drive and will allow a utility savings and green project that is anticipated to recover roughly 4,000,000 gallons of water annually for reclaim use on campus.

Immediate Street Traffic, Bike Lane, and Pedestrian impacts:

During the construction week, there will be traffic delays on Gilman Drive between Mandeville Lane and Osler Lane. Vehicles can expect intermittent closures on either the north or south bound lanes as well as delays on Eucalyptus Grove Lane at Bonner Hall and parking lot P113. Flaggers will be present to divert traffic during any closures. Bicycle lanes and pedestrian sidewalks will also be impacted. Please follow signage and allow extra time while traveling on Gilman Drive.

Please see the attached map for the impacted areas:

http://rmp-public.ucsd.edu/fdc/Alerts/BonnerHallPotholing_alertmap03.04.19.pdf

For construction related inquiries, please contact Project Manager, Rick Lyons at rnlyons@ucsd.edu or 858.822.4834 or Project Administrator, Chris Greenlee at cdgreenlee@ucsd.edu or 858.822.2983. Thank you for your patience during these construction activities.



Eric C. Smith, P.E.
Associate Vice Chancellor
Capital Program Management