SUBJECT:    CONSTRUCTION ALERT – Revelle Utilities Improvements: Scholar Drive Traffic Impact

Project Location/Description:

Revelle Utilities Improvements will occur the week of July 29 through August 02, 2019 between the hours of 7:00am to 4:00pm. Potholing will locate existing underground utilities on Scholar Drive, between Keeling Apartments and York Lane.

The project will construct underground domestic water and sewer lines, a medium voltage electrical duct bank and will provide additional water, sewage capacity and bring power closer to existing facilities and any future improvements in the Revelle College area.

Immediate Street Traffic, Bicycle and Pedestrian Impacts:

Vehicular traffic may experience intermittent delays when Scholars Drive is reduced to one-lane. Flaggers will be present to direct traffic, pedestrians and bicycles, as needed. Please follow signage, proceed with caution and allow extra time for travel in this area.

Please view the area map at:
http://rmp-public.ucsd.edu/fdc/Alerts/revelleutility_alertmap_7122019.pdf

If you have any questions, please contact Project Manager Nicole Cheng at nmcheng@ucsd.edu or (858) 822-1874 or Project Specialist Kathy Whelan at klwhelan@ucsd.edu. We greatly appreciate your patience during these construction activities.



Eric C. Smith, P.E.
Associate Vice Chancellor
Capital Program Management