UC San Diego Campus Notice
OFFICE OF THE ASSOCIATE VICE CHANCELLOR 
CAPITAL PROGRAM MANAGEMENT
October 15, 2021
Geisel library at sunset
ALL ACADEMICS, STAFF AND STUDENTS AT UC SAN DIEGO

CONSTRUCTION ALERT – Humanities and Social Sciences Building Repair – Temporary Closure of Scholars Lane, Parking Lot P201 and Biology Building Loading Dock

Project Purpose
Construction impacts will occur along Scholars Lane for removal of the mobile crane used for the Humanities and Social Sciences Building Repair project.

Location and Duration
Scholars Lane, Parking Lot P201 and the Biology Building loading dock will be temporarily closed from October 25, 2021 to October 29, 2021.

Immediate Parking Lot, Street Traffic and Pedestrian Impacts
  • Scholars Lane will be closed.
  • Access to Parking Lot P201 will be closed.
  • Access to the Biology Building loading dock will be closed.
  • Pedestrian traffic across Scholars Lane will be routed around the Muir Basketball Courts.
Please observe all temporary traffic controls and crewmember instructions. Please reduce speeds and allow extra space when traveling adjacent to construction activity. See a map of the affected area.  

If you have any questions, please contact Project Manager Brad Phipps at 858-228-6741. We greatly appreciate your patience during these construction activities.

Eric Smith, PE
Associate Vice Chancellor Capital Program Management
University of California San Diego, 9500 Gilman Drive, La Jolla, CA, 92093
This email was sent to .
To continue receiving our emails, add us to your address book.
ucsd logo