OFFICE OF THE ASSOCIATE VICE CHANCELLOR
CAPITAL PROGRAM MANAGEMENT

July 16, 2025

Alternate text

ALL ACADEMICS, STAFF, AND STUDENTS AT UC SAN DIEGO

REVISED CONSTRUCTION ALERT - SIO Automatic Load Shed System

***Revision: Impacted area extended and new duration of closure time.

Project Purpose: Perform medium voltage splices in the designated manholes as well as pull medium voltage cables from manhole E-10-11-14 at Revelle Switch Station down to manhole E-10-11-7 on Expedition Way.

Location and Duration: The work will start on August 1. The impacted area will cover from Revelle College Drive down to Expedition Way. Project completion is anticipated to be October 15th, 2025. 

See map of the affected area.

Immediate Parking Lot, Street Traffic, and Pedestrian Impacts:

  • The area from Revelle College Drive to Expedition Way will have delays with traffic control.

Please observe all temporary traffic controls and crewmember instructions. Please reduce speeds and allow extra space when traveling adjacent to construction activity. See a map of the affected area. If you have questions, please contact Project Manager Rosalie Pham (858) 232-5896. We greatly appreciate your patience during these construction activities.

Amy Engel
Senior Director
Capital Program Management

University of California San Diego, 9500 Gilman Drive, La Jolla, CA, 92093